🗓 Fallen Angel Production Timeline
Batch 1 – 3,900 Pieces (International + Domestic)
Production Start Date: 1st April 2025
Date | Milestone | Details |
---|---|---|
10 April 2025 | Fabric Ordered | Material sourced for all 3,900 pieces |
13 April 2025 | Cutting & Stitching Begins | Base structure work starts |
20 April 2025 | Embroidery Process Begins | Detailed embroidery work kicks off |
1 May 2025 | Washing Stage | Pre-finishing & quality checks begin |
10 May 2025 | Dispatching Started | Batch 1 shipping initiated |
Batch 2 – 2,490 Pieces (Domestic Only)
Production Start Date: 15th May 2025
Date | Milestone | Details |
---|---|---|
20 May 2025 | Fabric Ordered | Material sourced for 2,490 pieces |
25 May 2025 | Stitching Begins | Initial assembly work starts |
29 May 2025 | Pre-Finishing Stage | Final cut adjustments & prep |
1 June 2025 | Embroidery Starts | Artwork detailing process begins |
12 June 2025 | Dispatching Started | Batch 2 deliveries in progress |
Batch 3 – TBD
Production Start Date: 20th August 2025
-
Production updates will be shared soon.